Apr
21
Ottawa Colocation... Yes! It's coming! Hopefully this summer! Yes we'll be offering it, and a few other new services too! 2011 is going to be an exciting year 'round here... Stay tuned...

Posted by: Myke |

Apr
04
Diesel Day 2011-04-09 (Toronto Datacenter) As per every year:

Date: April 9, 2011
Time: 06:00hrs-22:00hrs EST.
Issue: 2011 ANNUAL SHUT-DOWN

* 151 Front Street will be performing their annual building shut down.

During the above maintenance window, all commercial power to the building will be disconnected for maintenance and upgrades. All suites will transfer to Generator Power for the duration of the window.

**NO SERVICE INTERUPTION IS EXPECTED, HOWEVER, THE ENTIRE BUILDING WILL BE ON GENERATOR POWER ONLY DURING THE ABOVE NOTED MAINTENAINCE WINDOW. ANY DISRUPTION TO THE GENERATOR(S) MAY CAUSE A LOSS OF POWER TO THE CUSTOMERS CONNECTED TO THE SAME. IT IS ADVISED THAT ALL CLIENTS PROTECT AGAINST ANY UNFORSEEN LOSS OF POWER**

Unless otherwise indicated, the scope of work to be performed by the building will include:

  • The utility will manually initiate the P&C transfer scheme to transfer power from 1AWR to A2WR and verify operation
  • manually transfer back from A2WR to A1WR
  • verify transfer
  • battery power will be used to operate the HV equipment during the test
  • of the transfer scheme in order to validate function and capacity
  • Document times and findings
  • Power transfer at Windsor sub-station
  • open A1WR-transfer to A2WR
  • verify successful transfer
  • close A1WR
  • open A2WR
  • verify successful transfer back to A1WR
  • High voltage testing to all main switchboard services
  • Complete inspection of all Hydro Vault electrical services
  • Repair of any deficiencies uncovered during the required inspection

Posted by: Myke |